March 2024#
| Volume | Part | Section | Change type | Description of change |
|---|---|---|---|---|
| 4 | 8 | All | Amended | Alignment with the current AS/NZS 3000 and AS 3017 (TRUM Vol 4 Part 8). |
| 1 | 15 min-Load added as a field (Electrical CoT) - This could be implemented using a clamp meter to measure current or using a power meter. | |||
| 4 | ELV fault loop impedance added (d.c. resistance measurement) (CoT). | |||
| 5 | Introduction of ELV into EFLI calculations tables (TRUM Vol 4 Part 8). | |||
| 5 | Introduction of 2A fuse in EFLI calculations, used in Traffic Signal Controllers (TRUM Vol 4 Part 8). |