13Testing, commissioning and configuration requirements#
After the signs are first built and before being used onsite, Factory Acceptance Tests (FAT) shall be completed in accordance with the requirements of this Technical Specification. Witness Point 2
The testing documentation for each sign used onsite shall be provided to the Principal when submitting the Traffic Guidance Scheme (QGTM Part 10) in accordance with Clause 5.3.2 of MRTS02 Provision for Traffic.
The generic Installation Acceptance Test (IAT), Commissioning Test (CT) and Customer Acceptance Test (CAT) shall be replaced with the Contractor’s configuration process. The minimum general requirements for this process are detailed in MRTS201 General Equipment Requirements.