Relationship table (harmonised to AGTTM08-19 Edition 1.0)#
| Section | Description | Applicability |
|---|---|---|
| 1 | Introduction | |
| 1.1 | Purpose | Accepted |
| 1.2 | Structure of AGTTM | Accepted |
| 1.3 | Scope of Part 8 | Accepted |
| 1.4 | Application of Part 8 to New Zealand | Accepted |
| 1.5 | Acronyms | Accepted |
| 1.6 | Definitions | Accepted |
| 2 | Road categories for temporary traffic management | |
| 2.1 | General | Accepted |
| 2.2 | Default TTM road categories | Accepted, with amendments |
| 2.3 | Project specific amendments to TTM road categories | Accepted |
| 2.4 | Road categories map for Queensland | New |
| 3 | Process for TGS selection | |
| 3.1 | General | Accepted |
| 3.2 | Generic TGS | Accepted, with amendments |
| 3.3 | Site suitable TGS | Accepted, with amendments |
| 3.4 | Site specific TGS | Accepted |
| 3.5 | TGS type selection | Accepted, with amendments |
| 4 | TTM approval activities | |
| 5 | Powers, roles and responsibilities | |
| 5.1 | Legislative context | Accepted |
| 5.2 | Statutory health and safety responsibilities – duty of care | Accepted |
| 5.3 | Application of the Parts of AGTTM | Accepted |
| 5.4 | Roles and responsibilities | Accepted, with amendments |
| 5.5 | Roles and responsibilities for special applications | Accepted |
| Section | Description | Applicability |
|---|---|---|
| 5.5.1 | Road safety barrier systems | Accepted with amendments |
| 5.5.2 | Austroads Safety Hardware Training and Accreditation Scheme (ASHTAS) | New |
| 5.6 | Supervising a Traffic Controller (TC) in training | New |
| 6 | TTM training framework | Accepted, with amendments |
| 6.1 | Application of TTM training framework | Accepted, with amendments |
| 6.2 | Training roles | Accepted, with amendments |
| 6.3 | Training by road category | Accepted, with amendments |
| 6.4 | Training – general | Accepted, with amendments |
| 6.4.1 | Competencies | Accepted, with amendments |
| 6.4.2 | Assessment | Accepted, with amendments |
| 6.5 | Traffic controller | Accepted, with amendments |
| 6.5.1 | Training by road category | Accepted, with amendments |
| 6.5.2 | Competencies | Accepted, with amendments |
| 6.5.3 | Progression between categories | Accepted, with amendments |
| 6.6 | Traffic management implementer | Accepted, with amendments |
| 6.6.1 | Training by road category | Accepted, with amendments |
| 6.6.2 | Competencies | Accepted, with amendments |
| 6.6.3 | Progression between categories | Accepted, with amendments |
| 6.7 | Traffic management designer | Accepted, with amendments |
| Section | Description | Applicability |
|---|---|---|
| 6.7.1 | Training by road category | Accepted, with amendments |
| 6.7.2 | Competencies | Accepted, with amendments |
| 6.7.3 | Progression between categories | Accepted, with amendments |
| 6.8 | Practitioner and non-practitioner status | Accepted, with amendments |
| 6.9 | Maintenance of qualification currency | Accepted, with amendments |
| 7 | Standard forms | |
| 8 | Model contract specification | |
| Appendices | ||
| A | TTM roles – additional tasks and activities | Accepted, with amendments |
| Table A1: Engineer | Accepted | |
| Table A2: Project manager | Accepted | |
| Table A3: Traffic management designer | Accepted | |
| Table A4: Traffic controller | Accepted | |
| Table A5: Traffic management implementer | Accepted with amendments | |
| Table A6: Principal contractor | Accepted | |
| Table A7: Traffic management worker | Accepted, with amendments | |
| B | Standard forms – examples | |
| B.1 | Form B.1 – TMP suitability checklist | Accepted |
| B.2 | Form B2 – Traffic management for roadworks operational check / onsite pre-opening inspection – checklist | Accepted |
| B.3 | Form B3 – Worksite traffic management – hierarchy of safety controls – checklists | Accepted |
| B.3.1 | Using the checklist | Accepted |
| B.3.2 | Form B3 – CHECKLIST PART A – Traffic controls assessment | Accepted |
| B.3.3 | Form B3 – CHECKLIST Part B – Justification for control selection | Accepted |
| Section | Description | Applicability | |
|---|---|---|---|
| B.3.4 | Form B3 – CHECKLIST Part C – Additional site-specific safety hazard / risk factors | Accepted | |
| B.4 | Form B4 – TMP daily traffic management diary | Accepted | |
| B.5 | Form B.5 – Traffic Management Plan (TMP) – long form | Accepted | |
| B.6 | Form B.6 – Design exception | Accepted | |
| B.7 | Form B.7 – Example of site condition rating (SCR) form – compliance inspection | Accepted | |
| B.8 | Form B.8 – Example of site condition rating (SCR) form – compliance inspection – short form | Accepted | |
| B.8.1 | Examples of ratings (short audit) | Accepted | |
| B.9 | Form B.9 – Example of notice of non-conformance | Accepted | |
| B.10 | Form B.10 – Example of notification of road closure / lane closure | Accepted | |
| B.11 | Form B.11 – Report on incident at roadworks site | Accepted | |
| B.12 | Form B.12 – Newspaper advertisement standard | Accepted | |
| C | Sample temporary traffic management specification template local government roads | ||
| C.1 | Specification | Accepted | |
| C.1.1 | Location and description of work | Accepted | |
| C.1.2 | Extent of work | Accepted | |
| C.1.3 | Setting out the works | Accepted | |
| C.1.4 | Scope of work | Accepted | |
| C.1.5 | Traffic guidance scheme (TGS) | Accepted | |
| C.1.6 | Record keeping and audit requirements | Accepted | |
| C.1.7 | Emergency and public transport vehicles | Accepted | |
| C.1.8 | Numbers of traffic controllers | Accepted | |
| C.1.9 | Traffic management plans | Accepted | |
| C.1.10 | Arrangement of traffic control devices | Accepted | |
| C.1.11 | Adequate traffic control devices | Accepted | |
| C.1.12 | Opening completed work | Accepted | |
| C.1.13 | Use of 40 km/h speed zoning | Accepted | |
| C.1.14 | Flashing arrow signs | Accepted | |
| C.1.15 | Message boards | Accepted | |
| C.1.16 | Water filled delineators and crash barriers | Accepted | |
| C.1.17 | Barrier boards | Accepted | |
| C.1.18 | Cones and bollards | Accepted | |
| C.1.19 | Traffic signals | Accepted | |
| C.1.20 | Devices to be safely supported | Accepted | |
| C.1.21 | Permanent traffic signals | Accepted | |
| C.1.22 | Alternative duties | Accepted | |
| C.1.23 | Control of worksites | Accepted | |
| C.1.24 | Compliance with standards, handbooks and guides | Accepted | |
| C.1.25 | Safety | Accepted | |
| D | Sample temporary traffic management specification template State / Territory Government roads | ||
| D.1 | Scope | Accepted | |
| D.1.1 | General | Accepted | |
| D.1.2 | Traffic management plan | Accepted | |
| D.2 | Temporary traffic management (TTM) personnel | Accepted | |
| D.2.1 | Authority to direct traffic | Accepted | |
| D.2.2 | Traffic management implementer | Accepted | |
| D.3 | Planning and design | Accepted | |
| D.3.1 | General | Accepted | |
| D.3.2 | Hazard identification, risk assessment and control | Accepted | |
| D.3.3 | Objective and targets | Accepted | |
| D.3.4 | Temporary speed zoning | Accepted | |
| D.3.5 | Least possible disruption | Accepted | |
| D.3.6 | Maintain access to adjoining properties and side roads | Accepted | |
| D.4 | Road occupancy licence | Accepted | |
| D.4.1 | Road occupancy licence application | Accepted | |
| D.4.2 | Road occupancy fees | Accepted | |
| D.4.3 | Licence conditions | Accepted | |
| D.5 | Traffic management plan (TMP) | Accepted | |
| D.5.1 | Plan submission | Accepted |
| Section | Description | Applicability |
|---|---|---|
| D.5.2 | Required elements | Accepted |
| D.5.3 | Plan preparation | Accepted |
| D.5.4 | Contractor's responsibility | Accepted |
| D.6 | Traffic staging plans | Accepted |
| D.6.1 | General | Accepted |
| D.6.2 | Required details | Accepted |
| D.6.3 | Safety barriers | Accepted |
| D.7 | Traffic Guidance Schemes | Accepted |
| D.7.1 | Plan submission | Accepted |
| D.7.2 | Generic traffic guidance schemes | Accepted |
| D.7.3 | Project specific traffic guidance schemes | Accepted |
| D.7.4 | Required details | Accepted |
| D.8 | Vehicle movement plans and pedestrian movement plans | Accepted |
| D.8.1 | Vehicle movement plans | Accepted |
| D.8.2 | Pedestrian movement plans | Accepted |
| D.9 | Road safety audit of TMPs | Accepted |
| D.10 | Traffic management risk assessment workshop | Accepted |
| D.10.1 | General | Accepted |
| D.10.2 | Content of workshop | Accepted |
| D.10.3 | Participants | Accepted |
| D.10.4 | Close out identified risk issues | Accepted |
| D.11 | Temporary roadways and detours | Accepted |
| D.11.1 | Construction of temporary roadways and detours | Accepted |
| D.11.2 | Opening temporary roadways and detours to traffic | Accepted |
| D.11.3 | Road safety audit of temporary roadways or detours | Accepted |
| D.11.4 | Removal of temporary roadways and detours | Accepted |
| D.12 | Traffic control devices | Accepted |
| D.12.1 | Safety barriers | Accepted |
| D.12.2 | Pavement markings and signs | Accepted |
| D.12.3 | Portable variable message signs | Accepted |
| D.12.4 | Radar activated speed signs | Accepted |
| Section | Description | Applicability |
|---|---|---|
| D.12.5 | Temporary traffic signals | Accepted |
| D.13 | Monitoring of traffic control measures | Accepted |
| D.13.1 | Communication | Accepted |
| D.13.2 | Emergency preparedness and response | Accepted |
| D.13.3 | Incident investigation, corrective and preventative action | Accepted |
| D.14 | Side-tracks and detours | Accepted |
| D.15 | Opening to traffic upon completion | Accepted |