4.1.2Understanding contractor requirements#

Table 4.1.2 lists contractor requirements.

Table 4.1.2 – Contractor requirements
Nature of requirementDetail of requirement
Road Category2
Type of closureSingle lane (left lane)
Works durationSingle shift (night work) – maximum 6 hours
Work zone speed40 km/h is required due to worker proximity
Live traffic stoppageManually-operated boom barrier to stop traffic Required for ingress / egress and some works (maximum 10 minutes stopped at a time)
Posted speed100 km/h
Existing lane widthBoth lanes 3.5 m
Existing sealed shoulder1 m (both sides)
Existing unsealed shoulder1.5 m (both sides)
Work area50 m length of works (plus include an additional 50 m area for access / working room) = 100 m in total
Maximum traffic during works12 average vehicles and one large vehicle for a five-minute count.
Source: TN195 TGS Worked Examples · page 6 Open PDF at this page Search this document