6.1General#
A TGS shows all traffic control devices and their layouts on a plan and shall be consistent with the approved TMP.
Where any change to existing traffic arrangements is proposed, or where construction conflicts with normal traffic movements, the Contractor shall prepare a TGS which clearly details the revised traffic arrangements at all locations affected by the change or conflict. A separate TGS is required for each stage of the works where changes are made to the traffic control devices.
Traffic shall be controlled at all times, during construction, in accordance with the provisions of the Queensland MUTCD Part 3, QGTTM, TMWOR, the TMP and the TGS.
The requirements and recommendations set out in the Queensland MUTCD Part 3, QGTTM, TMWOR and this Technical Specification and its Annexure, do not preclude innovative or alternative traffic management solutions, as outlined in Clause 1.2.