4Quality system requirements#
4.1Hold Points, Witness Points and Milestones#
The quality system requirements defined in MRTS201 General Equipment Requirements apply to this Technical Specification. Additional Hold Points and Witness Points applicable to this Technical Specification are summarised in Table 4.1. There are no Milestones defined.
| Clause | Hold Point | Witness Point | Milestone |
|---|---|---|---|
| 4.2 | 1. Samples for acceptance (design). 2. Photometric performance certification. | ||
| 9.1 | 3. Barrow, tripod or trailer support structure design documentation. | ||
| 10 | 4. Detailed design documentation of the electrical wiring including charging assembly and calculations, signed by RPEQ. | ||
| 13 | 1. Factory Acceptance Test 2. PTSS Demonstration 3. ACMA Compliance 4. Site Acceptance Test |
4.2Samples for acceptance#
The requirements of MRTS201 General Equipment Requirements apply to this Technical Specification.
A sample PTSS for acceptance and photometric performance certification shall be provided 28 days prior to manufacture. Hold Point 1
Detailed designs of the PTSS layout, fabrication and assembly drawings, calculations, specifications and certifications of the PTSS and associated components (signed by the Contractor’s RPEQ) shall be submitted to the Principal via the Administrator for verification prior to manufacture.
Photometric performance testing methodology and NATA certification confirming the PTSS performance requirements specified in this Technical Specification shall be submitted before delivery to site. Hold Point 2