13Acceptance of work#

The Contractor must apply pavement marking which conforms with this Technical Specification, including the performance criteria specified in Clause 14.

If the work is Non-conforming at any time during the period during which the Contractor is responsible for the repair of defective work, the Contractor must reapply the pavement marking, at a time approved by the Administrator, so that it complies with the requirements of this Technical Specification.

In order to provide a uniform visual guide to the road user, all longitudinal lines within a 300 m segment must be replaced where the length of Non-conforming pavement marking exceeds:

  • a) 36 m continuous or 25% of total on any 300 m lane length on curves and barrier lines, or
  • b) 72 m continuous or 50% of total on any 300 m lane length on straights.

The Administrator may carry out its own field testing of the pavement marking for any requirement included in this Technical Specification.