Appendix CTest procedure – road lighting (circuits energised)#
This procedure details the required tests to be conducted for road lighting when main circuit is live.
Reference drawings
| Reference drawings | |
|---|---|
| Fig D | Road Lighting (Energised) Sheet 1 of 2 |
| Fig E | Road Lighting (Energised) Sheet 2 of 2 |
Refer to AS/NZS 3017 Fig 3.14 for full test sequence, where testing requiring no voltage to be applied has been substituted by obtaining current readings (test sequence d), part 2 following).
Procedure (in order of sequence)#
a)Visual inspection#
- i.Check for any dangerous vermin/biohazards in the switchboard.
- ii.Make sure the switchboard door and cabinet are correctly earthed.
- iii.Make sure the MEN link is available (if applicable).
- iv.Check all exposed conductors cannot be inadvertently accessed (IP2X).
- v.Look for mechanically damaged equipment, unsupported parts, and cables in tension.
- vi.Visually check all earthing conductors are connected to the earth bar.
- vii.Visually check that neutral conductors are connected to the neutral bar.
b)Earth continuity [no voltage test, but working in vicinity of live parts] (for poles can be omitted using alternative refer test sequence f))#
- i.Isolate supply and confirm no voltage present on load side of main switch and neutral.
- ii.Complete the following noting possible risk. Disconnect the main earth and MEN from the neutral link. Disconnection point is the earth bar.
- iii.Place Ohmmeter between the earth bar of the switchboard and the post of each road light using suitable trailing lead (of suitable length recommended).
- iv.If photo cell is located on a separate metal structure i.e. traffic signal post, then test earth continuity up to the photo cell.
- v.Record results (measure the resistance of the trailing lead also).
- vi.Reconnect the main earth and the MEN.
This test can be replaced by completing Earth Fault Loop Impedance test if traffic conditions do not permit use of a trailing lead
c)Insulation resistance test (via leakage current testing)#
Insulation resistance testing requires the supply to be disconnected; therefore, as per AS/NZS 3019 clause 4.7.4, leakage current test is to be conducted using a leakage current clamp meter.
- i.Simultaneously measure the current in the active and the neutral conductors under test.
- ii.If leakage current is greater than 10 mA then further testing is required to determine source.
d)Polarity test#
Test sequence part 1 – Voltage readings#
The following test sequence shall be completed with the supply on.
- i.Check operation of voltage indicator test unit.
- ii.Confirm main switch closed.
- iii.Connect one test lead to known earth.
- iv.Connect other test lead to terminals (one at a time) of switch.
- v.With switch ON, measure voltage. Voltage should be 230 – 240 Vac at both terminals.
- vi.Using the test lead referenced in step iv. make contact with other test lead to active and neutral terminal (one at a time).
- vii.With switch ON measure voltage. Voltage should be 230 – 240 Vac at active terminal, 0 Vac at neutral terminal.
- viii.Disconnect test lead from earth.
e)Correct circuit connections#
- i.Prove that the active, neutral and protective earthing conductors of each circuit are correctly connected so that there is no:
- short circuit between conductors
- transposition of conductors that could result in the earthing system and any exposed conductive parts of the electrical installation becoming live
- interconnection of conductors between different CCTS.
f)Earth Fault Loop Impedance (each light to be tested individually)#
- i.Confirm light switch is ON.
- ii.Connect Loop Tester at the road light on each run. Measure EFLI at load side of the switch.
- iii.Take two sets of readings, about 30 seconds apart.
- iv.Confirm results are same – otherwise test again.
- v.Record the type and size of the protective device.
g)Infrared thermal imaging#
- i.In accordance with AS/NZS 3019 Clause 5.8, equipment is to operate under normal operating loads for at least 30 minutes.
- ii.Measure the temperature of the equipment components using the infrared thermal imaging equipment.
- iii.Determine if any equipment is affected by excessive rise in temperature. If high temperature values are measured, rectify installation. Retest equipment components including use of infrared thermal imaging equipment.
