Item 20005Installation of Temporary Barriers#

Work Operations incorporated in the above item include:

  • a) Work Operations listed in Clause 2.1.5 of MRS01 Introduction to Specifications
  • b) maintenance and repair of barrier
  • c) supply of erection angle connectors, reinforced connector assemblies and connector tie bars, as necessary
  • d) trimming and/or levelling surface
  • e) erection of barrier, including water filling where required
  • f) dismantling and relocation of barriers, and
  • g) dismantling and removal of barrier from the site.