Item 20005Installation of Temporary Barriers#
Work Operations incorporated in the above item include:
- a) Work Operations listed in Clause 2.1.5 of MRS01 Introduction to Specifications
- b) maintenance and repair of barrier
- c) supply of erection angle connectors, reinforced connector assemblies and connector tie bars, as necessary
- d) trimming and/or levelling surface
- e) erection of barrier, including water filling where required
- f) dismantling and relocation of barriers, and
- g) dismantling and removal of barrier from the site.