20Handover#

Unless otherwise specified, as a condition of final handover from the Contractor to the Principal, all ITS infrastructure and devices shall successfully complete and pass the CAT as defined by the testing and commissioning plan. All additional tests directed by the Administrator or the Principal in accordance with the Contract (including those based on the operating and maintenance experience of the Facility) shall also be carried out by the Contractor.

20.1Audit of operations manuals#

As a condition precedent to final handover, the Contractor shall perform a complete audit and rectify accordingly, the accuracy / currency of the operations manuals, including:

  • a) data recorded during commissioning
  • b) as built drawings
  • c) purpose written software
  • d) electronic and hardcopy of all specific configuration settings of systems / devices
  • e) manufacturer's manuals (including maintenance manuals and procedures)
  • f) Electrical Verification Certificate
  • g) maintenance procedures developed by the Contractor, and
  • h) any other items requested by the Principal.

The Contractor shall make good any shortcomings in the Operations Manuals, including repairs, refurbishments or replacements performed by the Contractor during the Maintenance Period.

20.2Training#

As a condition precedent to final handover, the Contractor shall satisfy the training requirements specified elsewhere in this Technical Specification.

20.3Principal's maintenance manual#

As a condition precedent to final handover, the Contractor shall satisfy the requirements for maintenance and repair manuals for the Principal specified elsewhere in this Technical Specification.

Source: MRTS201 · pages 52–53 Open PDF at this page Search this document