13Testing and commissioning#

13.1General#

The testing and commissioning requirements defined in MRTS201 General Equipment Requirements apply to work provided under this Technical Specification. The minimum additional testing and commissioning requirements for equipment provided under this standard are described below.

13.2Factory acceptance tests#

The optical performance shall be determined by measurement under laboratory conditions of the minimum luminance ratio and the minimum and maximum luminance for all sign luminance levels listed in AS 4852.1 and in accordance with the photometric test procedures defined in AS 4852.1. The performance of the eTCS shall meet or exceed the parameters listed in AS 4852.1. Witness Point 1

Source: MRTS229 · page 21 Open PDF at this page Search this document