4Quality system requirements#

The quality system requirements are defined in MRTS201 General Equipment Requirements apply to this Technical Specification. Additional quality system requirements relevant under this Technical Specification are defined in Table 4.1

4.1Hold Points, Witness Points and Milestones#

General requirements for Hold Points, Witness Points and Milestones are specified in Clause 5.2 of MRTS01 Introduction to Technical Specifications.

The Hold Points, Witness Points and Milestones applicable to this Technical Specification are summarised in Table 4.1. There are no Milestones defined.

Table 4 – Hold Point, Witness Points and Milestone
ClauseHold PointWitness PointMilestone
4.21. Samples for acceptance (design) 2. Optical performance certification
10.13. Trailer and/or concrete block support structure design documentation
12.91. Optical performance certification

4.2Samples for acceptance#

Requirements of MRTS201 General Equipment Requirements apply to this Technical Specification. A sample TVSL sign for acceptance and optical performance certification shall be provided 28 days prior to sign manufacture. Hold Point 1

Detailed designs of the sign layout, fabrication and assembly drawings, calculations, specifications and certifications of TVSL signs and associated components (signed by the Contractor’s RPEQ) must be submitted to the Principal via the Administrator for verification prior to manufacture.

Optical performance test methodology and NATA certification confirming the TVSL sign performance requirements specified in this Technical Specification must be submitted before delivery to Site.

Hold Point 2

Drawings from the original pages