5Quality system requirements#

5.1Hold Points, Witness Points and Milestones#

General requirements for Hold Points, Witness Points and Milestones are specified in Clause 5.2 of MRTS01 Introduction to Technical Specifications.

The Hold Points, Witness Points and Milestones applicable to this Technical Specification are summarised in Table 5.1.

Table 5.1 – Hold Points, Witness Points and Milestones
ClauseHold PointWitness PointMilestone
8.21. Dismantling of items to be salvagedSubmission of schedule of items to be salvaged (seven days)
ClauseHold PointWitness PointMilestone
9.22. Dismantling of items to be re-erectedSubmission of schedule of items to be re-erected (seven days)
13.3.1.13. Alternative sign face material
14.2.1.34. Welding Personnel
14.4.11. Erection of road signs
165. Contractor's information signsSubmission of details of information signs (14 days)
19.4.66. Test section of extruded concrete traffic barrier
20.4.57. Material Conformance2. Test of steel where test certificates are not available
20.4.6.13. Selection of posts and panels for audit testing
20.4.6.38. Acceptance of materials prior to installation
20.5.29. Welding Personnel in Australia
20.6.710. Acceptance of Installation
21.211. Manufacture of Proprietary steel barrier
21.4.112. Acceptance of Installation
21.4.413. Acceptance of Tension Report4. Verification testing
22.1Submission of product details, and construction procedure
22.2.514. Alignment
22.2.65. Surface preparation
22.4Submission of TGSI warranty

5.2Construction procedures#

Construction procedures which are required to be submitted in accordance with Clause 6 of MRTS50 Specific Quality System Requirements are listed in Clause 2 of Annexure MRTS14.1.